Description: This project involved the installation of 8 timber deck/steel girder structure bridges 15M long each, steel pipe piles, precast concrete spread footings, and paving of approaches.
Click
thumbnails to view full size images of the Nautley River Bridge Project.
Client: Ministry of Transportation Location: Northern BC Project Dates: 1999 - 2000
Ruskin
Key Personnel:
Joseph Hanna
Rick Haws
Client
Contact:
George Lomas Ministry of Transportation