Site C Temporary Construction Bridge

Ruskin’s scope of work included design-build of a 10.2 meter wide by 329 meter long, pile supported, non-composite resource bridge to support the Site C dam project for BC Hydro. Bridge was designed by Allnorth Consultants and constructed in 120 production days; both day and night shift, working a seven / ten schedule. It was completed with zero lost time incidents or injures, with a total of 27,680 Man-hour’s. Project was completed two weeks ahead of schedule, on budget, and with no lost time incidents or injures.

Client
BC Hydro

Project Schedule
Dec 2015 – Mar 2016